Dam Removal Delayed Due To High Water Levels

Due to the many storms and rain accumulation of the past 24 hours, the first cut into the Sheraton dam is delayed.  We apologize for this delay; however, with the current water level at 1,130 cubic feet per second, it is not safe for the crew to begin.  

The preparation and staging for the removal is complete; construction can begin when the water level drops down to around 200 cubic feet per second.

Visit our website, www.cityofcf.com to see our "Dam Cam" and watch for continuing updates.